一、编制依据 ······································································· 1 二、工程概况 ······································································· 1 三、材料及其要求 ································································· 1 四、外脚手架构造 ································································· 2 五、节点构造 ······································································· 3 六、脚手架的设计计算 ··························································· 4 七、脚手架的搭设 ································································· 10 八、脚手架搭设的技术要求及允许偏差 ······································ 12 九、脚手架的拆除 ································································· 13 十、脚手架防电、避雷及安全防护装置 ······································ 14 十一、脚手架验收与保养 ························································ 15 十二、外架施工现场管理 ························································ 20 十三、安全措施及要求 ··························································· 20 十四、脚手架工程组织机构及人员安排 ······································ 21
1
个人收集整理 仅供参考学习
外 脚 手 架 施 工 方 案
一、编制依据
1、包西铁路通道延安车站改造工程(站房)工程设计施工图纸; 2、国家、行业现行有关技术、荷载规范、规程标准及图集; 3、施工手册第四版(缩印本); 4、同类工程施工资料及相关工法;
二、工程概况:
总建筑面积23987 m2,其中地上20629.16 m2,地下3357.84 m2。包括进站大厅、候车室、售票房、行包房、旅客服务设施、客用管理用房、车站办公和技术作业场所用房。站房建筑物长264m,宽53.6m,高度分别为25.7m(两端的坡屋顶屋脊),29.1m(中间部分屋面)。站房地上二层,局部设夹层。一层层高8m,二层层高7.4m。在二层与屋面之间设有夹层,层高6.5m。其中D~○J,29~○42为地下一层人防地下室。结构层高4.2m,建筑层高3.9m。 ○○
三、材料及要求 1、钢管
钢管包括立杆、大横杆、小横杆、剪刀撑、附墙杆等。
钢管采用外径为48mm,壁厚3.5mm,其材质应采用国家现行标准《直缝电焊钢管》(GB/T13793)或《低压流体输送用焊接钢管》(GB/T3092)中规定的3号普通钢管,其质量应符合GB700-79《普通碳素结构钢技术要求》中A3钢的要求。弯曲变形,锈蚀钢管不得使用。脚手架钢管每根1-6米,钢管上严禁打孔。 2、扣件
扣件包括直角扣件、旋转扣件、对接扣件及其附件、T型螺栓、螺母、垫
2
个人收集整理 仅供参考学习
圈等。
扣件及其附件应符合GB978-67《可锻铁分类及技术条件》的规定,机械性能不低于KT33-8的可锻铸铁的制作性能,其附件的制造材料应符合GB700-79中A3钢的规定,螺纹应符合GB196-81《普通螺纹》的规定,垫圈应符合GB95-76《垫圈》的规定。扣件与钢管的贴合面必须严格整形,保证钢管扣紧时接触良好,扣件活动部位应能灵活转动,旋转扣件的旋转面间隙小于1mm,扣件表面应进行防锈处理。脚手架采用的扣件,在螺栓拧紧扭力矩达65N·m时,不得发生破坏。 3、脚手板
脚踏板采用串式竹脚手板。 4、安全网
按照有关规范及部门的规定,本工程中的安全网采用密目式安全网满挂。 5、黄黑标志栏板
采用20cm宽标准黄黑栏板。每隔一层沿建筑物四周设置一道。 四、外脚手架构造:
本工程外脚手架分两部分搭设,地下室部分自-4.2M开始搭设,地下室以外部分自-1.4M开始搭设,地下室与非地下室脚手架交接处需连接牢固。脚手架的具体构造说明如下: 1、平面布置:
立杆纵向间距1500mm,横向间距1200mm,内排立杆距离建筑物的距离为350mm。立杆与大横杆必须采用直角扣件扣紧,不得隔步设置和遗漏。且立杆的直接头应相互错开0.5节长,其接头距离大横杆的距离不大于步距的1/3。 2、立面布置
大横杆步距1800mm,上下横杆的接长位置错开布置,错开距离不小于纵距的1/3,扶手杆水平设置于每步架1.2m高处。剪刀撑要求满设,并沿高连续布置,斜杆与立杆接触部位均用旋转扣件扣紧,其与水平杆的夹角在45°~60°之间,剪刀撑的节点应在同一水平和垂直线上,其接长必须采用搭接,搭接长度不小于400mm,且不少于三个扣件,除在两头与立杆和大横杆连接外,
3
个人收集整理 仅供参考学习
中间还增加2~4个节点。立杆和大横杆交点处须设一道小横杆。 3、斜道及人梯搭设
斜道坡度为1:3,宽度不小于1M,斜道脚手板应铺严,上面设厚3cm,间距不大于30cm的防滑条,转弯处搭设休息平台,宽度不小于1.2m,护栏高度1.2M。斜道设置在便于人员通行的脚手架外侧。用安全网封闭,外设踢脚板,通道两侧设置剪刀撑,进出口搭设防护棚,并悬挂标志牌。人梯设置为踏步梯,踏步尺寸为300×180mm,踏面及踢面均要求封闭且踏面上要求设置3cm宽,间距不大于30cm的防滑条。踏步宽为900~1000mm,转弯处设休息平台,其宽度不小于1000mm。人梯周围要设护栏,高度不小于1.2M。斜道及人梯均采用钢管搭设。斜道上铺设串式竹脚手板,下为间距30cm横向钢管龙骨及700cm纵向钢管龙骨,必要时钢管龙骨可加斜撑支于地面以增加刚度。要求竹脚手板必须与其下横向钢管龙骨用12#铁丝绑扎牢固。人梯采用废旧竹胶模拼接成踏步面及踢面,其下为横向双钢管龙骨锁于人梯斜杆上,斜杆角度按照踏步尺寸而定。必要时可在斜杆上再增设竖杆以增加斜杆的稳定。要求踏步面必须与其下钢管龙骨用12#铁丝固定牢固,踢面于踏步面用铁钉钉牢。 4、纵向水平杆的构造
纵向水平杆设置在立杆内侧,其长度不小于3跨。
纵向水平杆采用对接扣件连接,符合下列规定:纵向水平杆的对接扣件交错布置:两根相邻纵向水平杆的接头不宜设置在同步或同跨内,不同步或不同跨两个相邻接头在水平方向错开的距离不应小于500mm,各接头中心至最近主节点的距离不宜大于纵距的1/3。 5、横向水平杆的构造
主节点处必须设置一根横向水平杆,用直角扣件扣接且严禁拆除。主节点处两个直角扣件的中心距不应大于150mm。在双排脚手架中,靠墙一端的外伸长度,不应大于0.4L,且不应大于500mm。
作业层上非主节点处的横向水平杆,宜根据支承脚手板的需要等间距设置,最大间距不应大于纵距的1/2。 6、立杆的构造
4
个人收集整理 仅供参考学习
⑴.每根立杆下端设置在木垫板上。
⑵.脚手架必须设置纵横向扫地杆。纵向扫地杆应采用直角扣件固定在距底座上皮不大于200mm处的立杆上。横向扫地杆亦应采用直角扣件固定在紧靠纵向扫地杆下方的立杆上。 ⑶.脚手架底层步距为2.0m。
⑷.立杆必须用连墙杆与建筑物可靠连接。
⑸.立杆除顶层顶步可采用搭接外,其余各层各步接头必须采用对接扣件连接。对接应符合下列规定:
①.立杆上的对接扣件应交错布置,两根相邻立杆的接头不应设置在同步内,同步内隔一根立杆的两个相隔接头在高度方向错开的距离不宜小于500mm;各接头中心至主节点的距离不宜大于步矩的1/3。
②.搭接长度不应小于1m,应采用不少于3个旋转扣件固定,端部扣件盖板的边缘至杆端距离不应小于100mm。 脚手架构造简图详见附图一、二、三。 五、节点构造 1、连墙杆
为了增强脚手架的侧向刚度及稳定性,在外脚手架于建筑物之间设置连接杆,设置说明如下:
⑴.连接杆用短钢管制成,长度约500~800mm,一端用扣件固定于脚手架的立杆上,另一端与预埋钢管连接,且连墙杆均采用钢管。连接杆水平间距4.5m,按二步三跨设置,上下错开,成菱形布置。
⑵.连接杆尽可能设置在立杆与大、小横杆的连接处,与脚手架架体垂直,如在规定的位置上设置有困难,应在邻近点补足。
六、脚手架的设计计算 1、荷载计算
初步设计为:立杆横距b=1.2m,立杆纵距l=1.50m,内立杆距建筑物墙外皮距离b1=0.35m;脚手架步距h=1.80m。铺竹串片式脚手板层数为2层,同时进行施工层数为1层。
5
个人收集整理 仅供参考学习
脚手架与建筑主体结构连接点的布置,其竖向间距H1=2h=2×1.80=3.6m,水平距离L1=3l=3×1.50=4.5m,钢管为ф48×3.5。
恒载:
1) 脚手架结构自重(包括立杆、纵向水平杆、横线水平杆、剪刀撑、横向斜撑和扣件等自重):查施工手册第四版(以下简称手册)Gk=Gk1+Gk2+Gk3;Gk=Higk1+n1lagk2+Higk3
Hi—立杆计算截面以上的架高
a) 查手册表5-7(第194页)当步距为1.8m时每米立杆结构的自重标准值为:gk1=0.1089KN/m。则每步荷载为: Gk1=1.8×0.1089=0.196KN
2)作业层面上材料自重(包括串片式竹脚手板等材料的自重)查手册表5-10(第195页):由插入法当立杆纵距为1.5m时gk2=0.4637KN/m
Gk2=nlagk2=1×1.5×0.4637=0.696KN
3)外立面整体拉接杆件和防护材料的自重 查手册表5-11(第195页) gk3=0.0768KN/m
Gk3=Higk3=1.8×0.0768=0.138K 则Gk=0.196+0.696+0.138=1.03KN 活载
⑴.施工荷载:QK=3.0KN/m2,查手册表5-12(第196页)qk=1.8KN/m(施工荷载计算基数):则
QK=n1laqk=1×1.5×1.8=2.7KN 式中:QK——活荷载标准值。 ⑵.风荷载:
Wk=lawk式中:Wk——风荷载标准值(KN/m2),
——挡风系数,根据《建筑结构荷载规范》查封闭式脚手架取0.09;
la——立杆纵距1.5m
wk——脚手架风压标准值, wk=0.7μsμz w0
μz——风压高度变化系数,按现行国家标准《建筑结构荷载规范》(GBJ9)
6
个人收集整理 仅供参考学习
规定采用。地面高度为30m,取值为1.46。
μs——脚手架风荷载体型系数,对全封闭脚手μS=1.0,为按脚手架情况确定的挡风系数。
w0——基本风压,按照现行国家标准《建筑结构荷载规范》规定采用。延安地区为50年一遇值为w0=0.35KN/m2。
则wk=0.7μsμz w0=0.7×1×1.46×0.35=0.358KN Wk=lawk=1.5×0.09×0.7×1×1.46×0.358=0.0494KN 3、横向水平杆计算 ⑴.小横杆强度验算: 最不利荷载组合条件下的计算简图如下: q活q恒最不利荷载组合因为q恒所占比重较小,因此可偏安全简化,按下式计算Mmax:M1max8(q活q恒)b2 12 =8qb q=1.2(gK2·C+gK)+1.4KQQk·C 式中q2K2——脚手板自重,查表得, qK2=0.4637KN/m; C——小横杆间距,C=0.75;
gK——钢管单位长度的自重,查表得,gK=38.4N/m;
7
个人收集整理 仅供参考学习
KQ——施工活荷载不均匀分布系数,一般取KQ=1.2; Qk——施工荷载标准值,取3.0KN/m2;
q=1.2(464×0.75+38.4)+1.4×1.2×3000×0.75=4244N/m;
1Mmax42441.22=763.92N·m
8验算抗弯强度:
Mmaxf W式中:W——小横杆钢管净截面抵抗矩,由钢管规格ф48×3.5,查表得W=5080mm3。 所以:安全。
⑵.小横杆扰度计算
扰度按下式进行近似计算,可偏于安全:
5qb4v 384EI7639202
150.378<205N/mm 5080式中,E、I为钢管材料弹性模量和钢管截面惯性矩,查表得:E=2.06×105N/mm2,I=121900mm2,b为小横杆跨度,为1200mm。
5424410312004v4.563mm<1/150×1200=8mm 53842.0610121900小横杆扰度满足要求。 ⑶.扣件抗滑验算 小横杆支座处的剪力为:
V=4244KN/m×1.2m÷2=2.546KN<8KN 每个扣件抗滑按8KN进行验算。 4、纵向水平杆计算 ⑴.纵向水平杆强度计算
8
个人收集整理 仅供参考学习 可近似按下图进行计算:按三跨连续梁计算。 F1F1F1F1F1F1F1计算简图图中F1为小横杆与大横杆交点处支座反力的最大值。F1=bq/2=1.2×4244÷2=2546N 因为活荷载约占90%,因此可近似全按活荷载考虑: Mmax=0.213FL=0.213×2546×1.50=813.447N·m 8134475080160.127 ⑵.大横杆扰度验算 vb1.65FL2254615002100EI1.651002.06105121900=1/438<1/150 扰度满足要求。 ⑶.扣件抗滑验算 抗滑最大力为: 2546N×2=5.092KN<8KN 满足抗滑要求。 5、连墙杆计算 ⑴.稳定性验算: 由风荷载产生的连墙杆的轴向力设计值为: Nw=1.4SWwk=1.4×2×1.8×3×1.5×0.0494=1.12KN 连墙杆轴向力设计值按下列公式计算: Nl=Nw+3=1.12+3=4.12KN 9 个人收集整理 仅供参考学习 连墙杆计算长度,按最不利考虑为: l0=立杆横距+内立杆距外墙的距离=1.2+0.35=1.55m。 λ=l0/i=1550/15.8=98.1,根据λ查表5-38(第213页)得=0.624。 NlA4.1210000.62448913.502205N/mm2 ⑵.连墙杆抗滑验算: 根据Nl=4.12KN<8KN 满足抗滑要求。 6、脚手架搭设理论高度计算 立杆采用单立杆,脚手架搭设理论高度Hs按下列公式计算。 不组合风荷载: nKAf(1.2NGk21.4Nki)Hs= 11.2g k组合风荷载时: nAfcw(1.2NGk21.4NHQki)s= 11.2g k式中: k——考虑脚手架工作条件的结构抗力调整系数,可取0.725。 f——钢材的抗压强度设计值,采用205N/m2; A——立杆毛截面积,取489mm2; ——轴心受压构件的稳定系数,应根据长细比查表得:=0.243;λ——长细比,λ=l0/i=μh÷15.8=1.5×1800÷15.8=170.8; Mw——所计算立杆的风荷载设计值: M1.4WkLah21.40.04941.51.82w10=10=0.034KN·m fcm——考虑风荷载后钢材的抗压强度设计值。 10 个人收集整理 仅供参考学习 则不组合风荷载时: Hs= 0.7250.2434890.205(1.20.6961.42.7)=98.998m 1.20.1089最大允许搭设高度 [H]= Hs98.998=66.22m。 10.005Hs10.00598.998组合风荷载时: fcm= kf-MW/W=0.725×0.205-0.034/5.08=0.142 Hs= 0.1420.243489(1.20.6961.42.7)=93.8m 1.20.1089Hs93.8=63.853m 10.005Hs10.00593.8[H]= 最大允许搭设高度为63.853m。 本工程最大高度为29.1m,故本工程脚手架不需要卸荷,直接从地面开始搭设至顶部。 卸料平台必须与脚手架分开,独立搭设,详见附图四。 七、脚手架的搭设 1.施工准备 技术人员应熟悉上部图纸,熟悉各个部位及高度的结构变化,项目部应组织必要的物料进场,其中包括φ48×3.5mm钢管、对接卡口、直角扣件、旋转扣件和安全网等,以备外脚手架搭设使用;有关作业班组应组织足够的作业人员,准备外脚手架的搭设;同时在施工前,应当组织有关技术人员和安质人员对作业班组进行作业前技术、安全交底。架子工必须具备国家标准《特种作业人员安全技术考核管理规则》的条件,经过培训、考核、取得安全操作证并经体检合格后方可从事脚手架安装、拆除作业。 2.基础处理 地面夯实后再铺木方。 3.脚手架搭设要求 11 个人收集整理 仅供参考学习 外脚手架搭设的基本要求是:横平竖直、整齐清晰、图形一致、平竖通顺、连接牢固,受荷安全、有安全操作空间、不变形、不摇晃。 4.外脚手架的搭设顺序 外脚手架的搭设应严格遵循以下顺序: 铺木方→摆放扫地杆→逐根树立立杆并与扫地杆扣紧→装扫地小横杆并与立杆和扫地杆扣紧→装第一步大横杆并与各立杆扣紧→安第一步小横杆→安第二步大横杆→安第三、四步大横杆和小横杆→安连墙杆→接立杆→加设剪刀撑→铺脚手板→绑扎防护栏杆及挡脚板并挂安全网保护。 5、脚手架的搭设 脚手架的搭设除了按顺序搭设处,还得注意下列事项: ①按照规定的构造方案和尺寸进行搭设; ②及时与结构拉结或临时支顶,以确保搭设过程的安全; ③拧紧扣件(拧紧程度要适当); ④有变形的杆件和不合格的扣件(有长度、扣接不紧等)不能使用; ⑤搭设工人必须佩挂安全带; ⑥随时校正杆件的垂直和偏差避免偏差过大; ⑦没有完成的脚手架,在每日收工时,一定要确保架子稳定,以发生意外; 6、建筑物出入口处脚手架的搭设 建筑物出入口处的脚手架,应根据出入口的高度和宽度采用平行弦桁梁结构形式在开口处的两边要采用双立杆,悬空立杆下要设安全扣件,此处的连接要加密,每步设置,同时在洞口边及其上设置剪刀撑。 出入口脚手架的上方要有安全可靠的隔离防护设施,一般为在出入口处的外侧设置双层防护棚,防止物体堕落伤人,保护出入人员。 7、安全网 脚手架的外侧要满挂安全立网,立网的下口与立杆或建筑物要牢固的扎结,固定点的间距应不大于50cm,下边沿设挡脚板,上下两网之间的拼接要严密。立网平网与施工作业面边沿的最大间缝不得10cm。 8、搭设的一般规定 12 个人收集整理 仅供参考学习 ⑴.架子工应熟悉图纸,熟悉现场具体情况,了解技术交底意图和施工操作方法,并将符合要求的钢管、扣件等材料运至现场,分类存放,搭设前清除障碍物。 ⑵.架子工作业时,必须佩带好安全帽、系好安全带,严禁穿高跟鞋、拖鞋或硬底带钉易滑鞋作业,工具及零件应放在工具包内,服从指挥,集中思想、相互配合,拆除下来的材料不乱抛、乱扔。脚手架作业下方不准站人,并设专人监护。架子工不准在脚手架上打闹、嬉笑。 ⑶.凡遭遇六级以上大风或下雨天气时,不得进行作业。雨后作业应待脚手架上雨水吹干后进行,防止滑落。 ⑷.在靠近电源处拆除脚手架时,必须将电源先切断或严密防护,必要时变更位置后方可进行作业,不允许将电源线拉在脚手架上,以防止漏电伤人。 ⑸.不在脚手架上附装机械设备,悬挑平台拉缆风绳及搭(接)卸料槽(斗)等。 8、搭设规定 ⑴.搭设双排脚手架,先立里排立杆,后立外排立杆,立杆的垂直偏差不得大于1/200架高,相邻两根立杆接头错开500mm,并不在同一步距内。 ⑵.大横杆架设在立杆内侧,同一水平面的内外大横杆接头错开一跨距。大横杆水平偏差控制在50mm内。 ⑶.小横杆垂直置于大横杆之下,用扣件与立杆紧固连接,小横杆伸出大横杆之外,不应小于100mm,靠近一面,距离100~150mm,小横杆应水平、不得内高外低。 ⑷.剪刀撑的位置从脚手架两端开始连续设置,竖向全高。剪刀撑的斜杆设在立杆外侧,与大横杆成45°~60°夹角。 ⑸.为保证架子的稳定性,搭设剪刀撑时,将斜杆间隔的扣在立杆上和小横杆的伸出部分上。 ⑹.用对接扣件连接大横杆时,扣件的开口应朝向架子的内侧,螺栓朝上、以防雨水进入。用十字扣件时,开口不得朝下,以确保安全,在安装扣件时,必须将扣件放端正后再拧紧螺栓,拧紧螺栓时,用力要适当,一般控制在40~ 13 个人收集整理 仅供参考学习 50N·m。 ⑺.脚手架竹脚手板在操作层上应满铺、铺稳,两边用12#铁丝绑扎在大横杆上,防止滑动,严禁在护身栏杆外侧设站人竹脚手板。 ⑻.操作层脚手架设置栏杆与挡脚板,栏杆高度不低于1.2m,挡脚板用七夹板制成,高度不低于200mm。 ⑼.搭设脚手架必须严格按照规范要求选用材料,对于压扁、弯曲、锈蚀和有裂缝的钢管及不合格的构件,严禁使用,扣件螺栓应满足正常状态下的扭力矩要求(5~6kg·m)。 ⑽.为了防火安全,在每层上人跑道及建筑物对角处,各设置一个灭火器。 八、脚手架搭设的技术要求及允许偏差 序号 项目 表面 地基土质 1 地基基础 排水 垫板 底座 2 立杆垂直度:Hmax>30m 技术要求 坚实平整 允许偏差(mm) 符合技术要求 不积水 不晃动 不滑动下陷 Hmax≤100mm Hmax/400~600 步距偏差 3 间距 柱距偏差 排距偏差 4 大横杆高杆两端 差 扣件安装 ±20mm ±50mm ±20mm ±20mm ±10mm ≤150mm -50mm 14 同跨同一横截面内的高差 扣件距离中心节点 相邻立柱对接扣件高差 5 6 剪刀撑斜杆与地面的偏差 个人收集整理 仅供参考学习 7 脚手板外伸偏差、搭接 九、脚手架的拆除 0~50mm 脚手架使用完毕后立即拆除,在脚手架拆除前应作好以下工作: 1、对脚手架进行安全检查,确认不存在严重隐患。如存在影响拆除脚手架安全的隐患,应先对脚手架进行修整和加固,以保证脚手架在拆除过程中不发生危险; 2、在拆除脚手架时,应先清除脚手板(或竹笆板)上的垃圾杂物,清除时严禁高空向下抛掷,大块的装入容器内由垂直运输设备向下运送,能用扫帚集中的要集中装入容器内运下。 3、脚手架在拆除前,应先明确拆除范围、数量、时间和拆除顺序、方法、物件垂直运输设备的数量,脚手架上的水平运输、人员组织,指挥联络的方法和用语,拆除的安全措施和警戒区域; 4、严格遵循拆除顺序,由上而下、后搭者先拆、先搭者后拆,同一部位拆除顺序是:栏杆→竹脚手板→剪刀撑→大横杆→小横杆→立杆。 5、外脚手架的拆除一般严禁在垂直方向上同时作业,因此要事先做好其他垂直方向工作的安排; 6、拆除脚手架时,下部的出入口必须停止使用,对此除监护人员要特别注意外,还应在出入口处设置明显的停用标志和围栏,此装置必须内外双面都加以设置; 7、在拆除的脚手架周围,于坠落范围明显“禁止入内”字样的标志,并有专人监护,以保证拆脚手架时无其他人员入内; 8、对于拆除脚手架用的垂直运输设备要用滑轮和绳索运送或塔吊配合,严禁乱扔乱抛,并对操作人员和使用人员进行交底,规定联络用语和方法,明确职责,以保证脚手架拆除时其垂直运输设备能安全运转; 9、拆下的脚手架钢管、扣件及其他材料运至地面后,应及时清理,将合格的,需要整修后重复使用的和应报废的加以区分,按规格堆放。对合格件应及时进行保养,保养后送仓库保管以备今后使用; 10、本工程脚手架拆除时遇大风、大雨、大雾天应停止作业; 15 个人收集整理 仅供参考学习 11、拆除时操作人员要系好安全带,穿软底防滑鞋、扎裹腿。 12、脚手架拆除过程中,不中途换人,如必须换人,则应该在安全技术交底中交代清楚。 十、脚手架防电、避雷及安全防护装置 1.防电 ⑴.钢管脚手架不应搭设在距离外电架空线路的安全距离以内,安全距离见下表: 脚手架的外侧边缘与外电架空线路的边线间的最小安全操作距离 外电线路电压 最小安全操作距离(m) 1KV以下 4 1~10KV 6 35~110KV 154~220KV 330~500KV 8 10 15 ⑵.对于达不到上述规定最小距离时,必须采取防护措施,增设屏障、遮栏、围杆或保护网,并悬挂醒目的警告标志牌。 ⑶.脚手架搭设和使用期间,要严防与带电体接触,当需要穿过靠近380V以内的电力线路,距离线路在2m以内时,搭设和使用期间应断电或拆除电源,如不能拆除,应采取下列措施: ①对电线和脚手架分别采取有效的绝缘措施; ②对脚手架要采取可靠的安全接地处理; ③夜间施工时,应使用不超过12V电压的低压电源。 2、避雷 搭设脚手架时,应安装避雷针、避雷器、避雷线。 脚手架防雷接地,将建筑物上的避雷针引出与各段脚手架承载装置的四角焊接,接地电阻不大于10Q。 3、安全防护装置 ⑴、脚手架在施工楼面四周脚手跑道必须满铺竹脚手板,脚手板用12#铁丝同大横杆绑扎牢固,脚手架内排立杆与墙面之间铺设通长安全隔离七夹板或安全网。 ⑵、脚手架外侧满铺密目式防火安全网,并在外立杆里侧设置1.2m高的防护栏杆。 16 个人收集整理 仅供参考学习 ⑶、脚手架在搭设平架时,平架应外高内低,与水平面成15°角,伸出外立杆2.5m,斜杆与横杆均用φ48×3.5钢管搭设,上铺密目式安全网,用16#铁丝与横杆绑扎牢固。 ⑷、附设于外立面的塔吊卸料平台,应根据需要在垂直高度上错开设置,卸料台搭设构造如附图四。 十一、脚手架的验收与保护 (一) 脚手架在投入使用之前必须进行验收,合格后方准使用。 因为本工程的脚手架是随结构施工而往上搭设的,所以是分段搭设、分段投入使用。这就要求脚手架也必须分段进行验收,验收合格后方可投入使用。 检查验收的内容,应按施工组织设计或作业指导书的有关规定进行,外脚手架的验收主要有以下项目: 1.脚手架的基础; 2.脚手架的步高; 3.立杆的纵横间距,立杆的接头位置、立杆的竖直度; 4.立杆的纵横杆的标高、水平度、小横杆的交叉位置; 5.脚手板的固定; 6.安全栏杆的高度与道数; 7.剪刀撑的位置、距离、角度和搭接; 8.隔离设施、外挑安全网和外包安全网; 9.扣件的紧固程度; 10.连墙杆的位置,数量和牢固程度; 11.脚手架出入处的加固; 12.脚手架开口处的加固; 13.脚手架所用的钢管、扣件、型钢及其他材料的材质证明和抽检记录; 14.脚手架的接地防雷; 15.焊缝的质量。 外架必须验收检查合格后办妥脚手架验收手续,在脚手架醒目处挂上脚手架验收合格牌后,方可投入使用。 17 个人收集整理 仅供参考学习 在检查验收过程中,要特别注意扣件的紧固程度,扣件并不是拧得紧越好。对于拧紧力矩大于70N·M的扣件,要认真检查有无裂缝、变形,如果发现有上述弊病应立即调换,调上的扣件的螺栓应紧固在40~70N·M。 (二)脚手架在验收合格通过投入使用后,必须对其进行日常的保养和定期的全面检查和整修,才能保证其安全使用。 脚手架日常的保养和维修必须每天进行一次,定期的维护保养一般每月进行一次。所以要求作业队对外脚手架进行日常的和定期的保养和维修,尤其是每次强风、暴雨过后都要认真检查整修后方可使用。 脚手架保养整修的主要内容有: 1.检查脚手架基础有无不均匀下沉,脚手架底部有无堆放杂物; 2.检查明确手架的整体和局部的垂直偏差,特别要注意脚手架的转角处和断口处的垂直度。如发现垂直度有异常现象,应及时加固和消除隐患。 3.各类扣件的涂油和紧固。检查扣件时先检查扣件的外观,而后将扣件上的螺栓逆时针方向松几牙螺纹,再涂油紧固螺栓至规定的力矩范围内。 4.检查脚手板有否松动、悬挑,还要检查四角是否用铁丝扎牢,如发现问题应及时纠正。 5.与建筑物连接的检查,检查连接件是否齐全和完好,有无松动、移动。 6.要对外包安全网、外挑安全网、安全隔离设施、外侧挡板、栏杆和接地防雷等安全设施进行检查,保证这些安全设施完整、牢固,能正常发挥安全作用。如果有损坏者要及时调换,如有松动者应及时紧固,如发现松动和开口要及时连通。 7.如脚手架有开口、断口和出入口,应对该部位进行重点检查,使这些部位始终符合安全规定; 8.检查脚手架的荷载情况,使其不超过设计荷载,如有超载应及时卸荷至设计荷载。还要检查脚手架上堆物是否处于安全位置和稳定状态,如发现有处于不安全位置和不稳定状态应及时纠正。此外还要逐日清理脚手板上的垃圾。 9.脚手架的日常保养和定期检查,都要有记录。 18 个人收集整理 仅供参考学习 10、脚手架使用中必须经常检查,清除架子上的杂物,严禁在架子上堆积过多的施工材料,或多人挤在一起,以免架子发生超载,造成事故。 11、脚手架上施工材料应随用随运,施工荷载不得大于3000N/m2,使用机具、材料等尽量放在脚手架里侧,以减小倾覆力矩。 十二、外架现场施工管理 1、根据架立杆,水平拉杆及支承的位置,提前做好钢管,钢筋及穿墙管洞的预埋和预留,并做到标高一致,位置统一。 2、架体原则从转角处开始搭设,以建筑物转角为准,且于外侧立杆对应,横向间距不大于1300。 3、用钢管与预埋件焊接时,应将钢管与预埋件焊接牢固,以确保钢管有足够刚度。 4、外架钢管连墙杆按二步三跨梅花形间隔布置。 十三、安全措施及要求 1、所有操作人员应持证上岗,操作人员进入现场后,应做好进场三级教育,并做好会议记录,进行详细的安全技术交底。 2、每一楼层外架搭设完毕后,必须验收合格后方可使用。 3、防雷击接地措施,采用4×30镀锌扁铁与本建筑结构的四角避雷接地网焊接,其电阻不得大于要求的1Q。 4、高空作业要正确使用“三保”遇六级以上大风时,应停止高空作业。 5、及时收集气象资料,并通知全体施工人员,便于安排工作和进一步采取措施。 6、焊接作业时,要注意防火,遇风时,应设置挡风板,避免火花飞溅。 7、外架上不得堆放钢筋,模板等材料。 8、脚手架拆除程序与安装程序相反,拆除时,先将脚手架板逐一传递至楼层或转料平台上,再按步骤拆除,拆除步骤为横杆→立杆→剪刀撑,拆除时,严禁乱丢及高空坠物。 十四、脚手架工程组织机构及人员安排: 1、 组织机构如下: 19 个人收集整理 仅供参考学习 项目经理 ↓ 施工员、安全员 ↓ 脚手架施工技术人员 2、主要人员安排如下: ⑴.施工员3人:主要负责脚手架搭设、拆除的技术指导。 ⑵.安全员3人:主要负责脚手架的安全工作。 ⑶.脚手架技术工人30人:根据进度需要,主要负责脚手架的搭设、拆除工作。 ⑷.其他配合人员10人,主要负责协助垂直运输机械及操作人员钢管、扣件等的运输工作。 20 个人收集整理 仅供参考学习 附图26*19*钢丝绳M22花篮螺丝@1500满铺七夹板立杆@500撑杆@1500注:撑卸与预埋件焊接1.承料台位置,长度应根据实际需要确定,但上下位置必须错开。2.斜撑杆上端与大横杆应用双扣件连接.附图321 个人收集整理 仅供参考学习 包西通道延安火车站扩建工程 外脚手架施工方案 审核: 编制: 中铁十二局集团有限公司延安车站工程指挥部 2006年4月 1 因篇幅问题不能全部显示,请点此查看更多更全内容